Capital Project

Welcome to the Chenango Forks Central School District Capital Project. At CF, our commitment is to ensure transparency with our community members, stakeholders, and district families throughout this Capital project. Delve into the live timeline of our progress below, as we keep you informed every step of the way. Stay tuned for regular updates and more exciting information. The journey begins at the bottom of the page!
October 2025
September 2025
What's Happening:
-
Significant progress is underway with the installation of underground stormwater drains and structures, as well as the stone base to ensure proper drainage for the Baseball and Softball infields.
July 2025
What's Happening:
- Outdoor Basketball courts, High School Physical Education locker rooms and team rooms are complete
- Ongoing work this summer:
- New pool facility construction
- Area bathroom and locker room upgrades
- Drainage and site improvements & construction of a new baseball/softball complex
May 2025
October 2024
July 2024
October 2023
What's Happening:
- Proposal for new turf baseball and softball fields unveiled.
- New surfaces for basketball courts unveiled at CFE and CFMS
CAPITAL PROJECT VOTE: DECEMBER 12, 2023
September 2023
What's Happening:
- New Renderings have been released.
- Virtual Walkthrough of new Aquatic Center Revealed.
- All aspects of former pool and locker room areas demolished.
- Pool filled and leveled for new structure.
August 2023
What's Happening:
- Exterior walls and roof of pool & locker rooms have been removed
- MS basketball court has been stripped of old surfacing, prepped for new.
- CFE basketball court has been stripped of old surfacing, prepped for new
- New backboards added to each basketball court
July 2023
What's Happening:
- Pool building deconstruction
- MS Basketball court prepped for repaving
- CFE Basketball court prepped for repaving
Additionally, the CFCSD has started preparing a new referendum.