Welcome to the Chenango Forks Central School District Capital Project. At CF, our commitment is to ensure transparency with our community members, stakeholders, and district families throughout this Capital project. Delve into the live timeline of our progress below, as we keep you informed every step of the way. Stay tuned for regular updates and more exciting information. The journey begins at the bottom of the page!
July 2024:
What's Happening:
Renovations are underway for the new locker rooms
The former pool structure has been officially cleared to make way for the new facility
Grounds for the new pool facility are being prepped for construction
Blueprints can be found here:
HA42x30 (5) (boarddocs.com)
October 2023:
What's Happening:
Proposal for new turf baseball and softball fields unveiled.
New surfaces for basketball courts unveiled at CFE and CFMS
CAPITAL PROJECT VOTE: DECEMBER 12, 2023
September 2023:
What's Happening:
New Renderings have
been released
.
Virtual Walkthrough of new Aquatic Center Revealed.
All aspects of former pool and locker room areas demolished.
Pool filled and leveled for new structure.
August 2023:
What's Happening:
Exterior walls and roof of pool & locker rooms have been removed
MS basketball court has been stripped of old surfacing, prepped for new.
CFE basketball court has been stripped of old surfacing, prepped for new
New backboards added to each basketball court
Click HERE for presentation on new renderings!
July 2023:
What's Happening:
Pool building deconstruction
MS Basketball court prepped
for repaving
CFE Basketball court prepped for repaving
Additionally, the CFCSD has started preparing a new referendum.